Hey all, I'm running a mid-sized job shop, mainly aerospace and medical components, so we're constantly dealing with high-mix, low-volume orders. We've got a fantastic, newer 5-axis vertical mill that has been the biggest game-changer for cycle time, but it’s also become our biggest bottleneck due to non-cutting time. I ran the OEE report last week and the machine is sitting idle in Setup/Changeover for an average of 1.7 to 2 hours per 8-hour shift, purely on fixture swaps, tool presetting at the machine, and first-article check/prove-outs. This is crushing our capacity and making our quoted lead times longer than they should be, forcing us to run costly overtime just to stay competitive. We've started kitting tools beforehand and reviewing the setup docs, but the floor is still struggling with the physical work. For those of you running highly varied work, what specific, non-capital-intensive methods or workflows have you implemented to slash that changeover time down to under an hour? Is SMED really the answer, or is there a better way to stage fixturing off-line for a 5-axis machine? Open to hear your advice and suggestions. Thanks!